IMPORTANT NOTE:
This material can only be used as a reference.
The types of questions and number of questions for the final examinations vary
every year. For preparing the final examination, you should go through the
materials as described in the classes with the priorities as discussed by Dr.
Dai in the last class.
SAMPLE FINAL
QUESTIONS
Instructions:
1. All answers should be written on question paper provided
by circling the correct choice or writing in the spaces provided. You may write
on the back of the page if necessary.
2. Your answers should be written clearly and legibly.
3. This is a closed book exam. Tables and formulas are
provided. You should mention the table you are using to obtain your answer.
4. Calculations may be done on a separate sheet. However,
all sheets used are required to be submitted.
5. Calculators without programming functions may be used
for numerical calculations. Requirements for the use of the calculators are as
described in the class.
6. This examination constitutes 50% of the course grade.
____________________________________________________________________
PART A
(ANSWER ALL QUESTIONS)
FOR QUESTIONS 1 - 10, STATE WHETHER TRUE
OR FALSE:
1.
Waiting line theory
provides a means of forecasting arrival and service rates.
2.
The best way to evaluate
a job assignment situation with two machines is Johnson's method.
3.
It is best to use small
alpha values when forecasting a product whose real demand is erratic.
4.
The bill of materials
file contains a complete list of all materials currently on hand and on order.
5.
The ABC
classification is used to identify
components in the product structure tree of an MRP.
6.
Companies that are
called on monthly by vendor's sales representatives tend to use the fixed time
period reordering system.
7.
Assembly lines relate most
closely to a process layout.
8.
Central to the waiting
line problem is a trade-off decision - comparing the extra cost of providing
more rapid service with the costs of waiting.
9.
The utilization factor
in a waiting line system is the ratio of the service rate and the necessary
idle time.
10.
In the EOQ model, the
average inventory will always be Q.
FOR
QUESTIONS 11-15, SELECT THE BEST ALTERNATIVE:
11. Capacity
balance can be obtained by:
a.
buffer inventories
b.
decoupling through backup equipment
c.
adding capacity to bottleneck stages
d.
all of the above
e.
none of the above.
12. Linear
programming is useful principally in problems:
a.
which cannot be handled by a computer
b.
which can be solved graphically
c.
which require simultaneous solutions to many equations
d.
which are impossible to solve by other methods.
13. Which
of the following is a characteristic of critical path scheduling techniques?
a.
The jobs or tasks are dependent on each other.
b.
Interruptions may be permitted if they are documented.
c. The jobs or tasks must be well
defined, and their completion marks the end of the project.
d.
The jobs or tasks do not necessarily have to be in a predetermined sequence.
14. Fixed
order quantity models are:
a.
time triggered
b.
fixed for a specified time period
c.
made up of a variable order size
d.
event triggered.
15. The
reason for low level coding in MRP is:
a.
to show the relative importance of component items
b.
to make it easier for the computer to search
c.
to show the offset lead times in perspective
d.
so that the transaction files can be updated easily.
16. In the
Lamson case, when your team had a stockout in a given period, did you have to
fill or satisfy backorders? What extra information other than the actual sales
would have helped you to make better production decisions?
PART B (ANSWER ANY 5 QUESTIONS)
17. Fastcomp
buys computer chips from a supplier. The cost of a chip is $80 per unit; the
company incurs a cost of $1000 per order to process the order. Fastcomp has
determined that it costs 12% per year of an item’s cost to hold the item in
inventory. The lead time for delivery is 1.5 months. The company uses 120,000
computer chips per year. From historical data, Fastcomp believes the demand
during lead time is normally distributed with a mean of 15,000 and a standard
deviation of 2000. Determine the economic order quantity and the reorder point
for a service level of 98%.
18. Dr. Wu,
operations manager at Nesa Electronics, has to develop an assembly line balance
for a line assembling electric relays. The firm needs to produce 1400 electric
relays per work day. Due to breaks and lunch, there are 420 working minutes in
a work day. The following table lists the tasks, precedence relationships, and
average task time required to produce a relay.
TASK TIME
(sec) PRECEDING
TASK(S)
A 13 -
B 4 A
C 10 B
D 10 -
E 6 D
F 12 E
G 5 E
H 6 F,G
I 7 H
J 5 H
K 4 I,J
L 15 C,K
(a)
Compute the maximum
cycle time Nesa can have and still produce 1400 relays per day.
(b)
Compute the theoretical
minimum number of work stations required.
(c)
Use the ranked
positional weight technique (RPWT) to allocate tasks to work stations that
attempts to minimize the number of work stations while producing at least 1400
units per day.
(d)
For the solution in (c),
compute the actual cycle time and the actual production rate that would result.
(e)
Compute the efficiency
of the line balance in (c).
19. A
company manufactures two products A and B using three inputs, labor, material R
and material S. To make one unit of product A requires 6 lb. of R, 7.5 lb. S,
and 9 person-hours of labor. To make unit of B requires 12 lb. of R, 4.5 lb. of
S, and 6 person-hours of labor. The demands for the products are such that the
company can sell as much of each product as it can produce and earn a profit of
$3 per unit of A and $4 per unit of B.
However, only 900 lb. of R, 675 lb. of S, and 1200 person-hours of labor
are available to the company each day.
20. Andy
Arthurson is an independent computer software consultant. He has five jobs
awaiting completion. Following are the estimated work times required to
complete each job and the due dates requested by customers.
JOB PROCESSING
TIME DUE
DATE (DAYS (DAYS) FROM PRESENT)
A 12 52
B 16 37
C 8 28
D 20 57
E 6 31
(a) Develop a schedule for the above jobs using shortest
processing time rule. Calculate mean flow time and mean lateness for this
sequence.
(b) Develop a schedule using the critical ratio rule. Calculate mean flow time and mean lateness.
21. Acme
Advertising has decided to purchase two fax machines. Two departments, Design
and Sales, will be the primary users of the machines. Each department expects
to generate 36 documents per eight-hour day that need to be faxed; the timing
of these transmissions follows a Poisson distribution. The time it takes to
transmit each document is exponentially distributed with an average
transmission time of 10 minutes. Each department wants to have its own machine
to use exclusively (no other department can use it). The manager of Purchasing
wants the two machines to be in a common area that both departments can use.
Compare
the above two configurations in terms of (a) time in queue, (b) time in system
and (c) average number of items waiting in line to be transmitted. Comment on
the implications of your results.
22. The diagram below shows a product structure tree for product
A.
A
| .
|
|
B(2) C(1)
|
| .
|
| | | |
D(3) F(1) B(3) D(1) E(4)
|
| |
|
| | |
E(1) D(3) F(1) E(1)
|
E(1)
Additional
information about all the items is as follows:
Scheduled Beginning
Item Lead
time Lot Size Receipts Inventory
(weeks)
A 2 20 10
in wk 3 5
B 2 40 20
in wk 7 10
C 1 LFL* - -
D 3 160 - 100
E 2 LFL 60
in wk 2 100
F 2 LFL 40
in wk 5 -
(NOTE:
* LFL = Lot For Lot)
(a) Draw a Low-Level coded Product Structure
Tree.
(b) If 20
units of A are required in week 10, develop the MRP plan for items A, B, C, and
D, using the tabulated format shown below. for the gross requirements,
scheduled receipts, on hand from prior period, net requirements, planned order
receipt and planned order release.
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
Gross
requirements |
|
|
|
|
|
|
|
|
|
|
Scheduled
receipts |
|
|
|
|
|
|
|
|
|
|
On
hand from prior period |
|
|
|
|
|
|
|
|
|
|
Net
requirements |
|
|
|
|
|
|
|
|
|
|
Planned
order receipt |
|
|
|
|
|
|
|
|
|
|
Planned
order release |
|
|
|
|
|
|
|
|
|
|